|
Putting
The “Star” Back In Startex
Multiple
Partnerships Revitalizing Once Prominent Community of Startex
By Glenn D.
Bridges
Longtime residents of Startex can recall the days when a
thriving textile mill had the community bustling with prominent
textile-league ball teams, stores, a barbershop, grand hotel,
attractive lakeside homes and much more.
Today, it’s a
mere shell of its former self, but thanks to a relatively new
organization – the Startex/Tucapau Community Action
Association – the town is undergoing a major metamorphosis.
|

Main
Street Startex, is currently undergoing a major
"underground" metamorphosis as its aging and
antiquated water system is being replaced and significantly
upgraded.
Photo
by Glenn D. Bridges |
Formed a little
over two years ago, STCAA is currently overseeing one of its
biggest revitalization projects yet through a partnership with
at least six parties, including the SJWD (Startex, Jackson,
Wellford, Duncan) Water District, Startex Fire Department,
Spartanburg County Community & Development Department, Town
of Lyman, federal government and a major developer who has
invested a substantial amount of his own money into replacing an
aging and dangerously antiquated water system.
“We’ve
talked about this for probably four years and finally began
pursuing it,” said STCAA President David Gregg. “
Spartanburg
County
came to the table a little over two years ago and told us they
were interested. They did a revitalization project in Una, and
when it was completed, they told us they were coming to
Startex.”
Through grants
and the non-profit Christmas In Action organization, numerous
homes in the community underwent repairs and upgrades this past
spring. Now the focus has shifted to the water system.
|

|
|
This
aging and now defunct fire hydrant is one of several
dotting the streets of Startex that are tagged with
signs stating "Out of Service." A major
revitalization of the water infrastructure in Startex
will add numerous new fire hydrants and lower
homeowners' insurance rates.
Photo
by Glenn D. Bridges |
One of
the biggest issues is a lack of fire hydrants and efficient
waterlines. Thus SCCDD applied for several federal grants in
conjunction with SJWD, which were approved.
“There are
actually a lot of fire hydrants out there, but when the mill
closed, it shut down the system it had maintained in the
community,” said Billy Cothran, SJWD director of engineering.
“Most of the domestic lines, which are small, were abandoned.
After there was a fire in the community, we made a temporary
tie-in (via the Town of
Lyman
) and added a couple of fire hydrants to protect the churches
and a couple of other properties. After this project is
completed, all of the lines will have been replaced and
there’ll be 14 more hydrants so that everyone is covered.”
Currently,
dozens of decrepit hydrants dot the landscape tagged with “Out
of Service” signs, and the system is in receivership through
Lyman. SJWD wants to take it out of receivership and make it
part of their district.
“The lines
are really small, plus there’s debris in them, so there’s
not enough water pressure,” said Mallory Beckett, a SCCDD
planner working in liaison with SJWD and the town. “We’re
very pleased with how the project is going. SJWD wants to make
sure it comes to fruition.”
Another perk is
that with more hydrants, homeowners’ insurance rates should
drop considerably, so it’s a big deal for Startex, Beckett
claims.
|

|
|
A
new fire hydrant, one of at least seven planned for Main
Street Startex, is partially visible behind a bundle of
hay used to hold loose soil in place.
Photo
by Glenn D. Bridges |
Managing the
construction end of the project for the county is Holland Belue,
who said the mission is divided into two phases.
“Phase One
runs from Highway 290 to
Main Street
in Startex and up to
Spartanburg Road
,” he explained. “That’s about 10,500 feet. We’re also
burying the pipeline under the sidewalks because it’s a lot
cheaper to replace than asphalt. That’s approximately 4,000
feet of sidewalk and gutter work that will have to be
replaced.”
According to
Gregg, SJWD also agreed to do something it normally doesn’t
do.
“They plan to
make the sidewalks wheelchair and handicapped accessible –
something we don’t have right now,” he said. “They also
plan to do some work around the Post Office with the same thing
in mind. It’ll improve the looks of the community as well as
make it more efficient.”
Belue said
Payne, McGinn & Cummings was awarded the $800,000 Phase One
project. Seven new fire hydrants will increase the fire
department’s ability to serve
Main Street
and the old mill. The work began in earnest in August, with a
completion goal of 100 days.
The county has
awarded SJWD a $400,000 Community Development Block Grant to do
the service lines on the side streets in Phase Two.
|

A
12-inch trunk line was recently installed on Spartanburg
Road near Hickory Drive in Startex as part of a major
revitalization effort to replace the mill village's
aging and inadequate water system.
Photo
by Glenn D. Bridges |
SJWD is also
using a bond referendum. That phase will add another 12
hydrants, and could cost an additional $400,00 to $500,000 if
SJWD hires a contractor for the labor.
“We’ll
systematically link the lines to each house,” said Cothran,
who estimates it’ll take two to three hours per house.
The City of
Lyman
also received a $400,000 grant to improve sewer services.
“This project
is on a whole new level than what we’re accustomed to based on
the size of the community and having to install over 300
meters,” Cothran added. “But we’re getting a better system
ourselves, and Startex is definitely better off.”
Resident
Crystal Presley agrees.
“They post
updates down at the Post Office, and everyone is talking about
it,” said Presley, as she and her children strolled down a
sidewalk. “We’re excited, and I haven’t heard any
complaints.”
Another major
player is Paul (Satpal) Rathie, owner and operator of Lake
Construction LLC, who purchased the Startex Mills property when
it went bankrupt. After learning the
Main Street
infrastructure would feature eight-inch pipes, he donated
$100,000 to upgrade to a 12-inch trunk line to accommodate
future growth.
|

Startex
is undergoing a major transformation in both services an
appearance as several groups are working together to
revitalize the one thriving mill village.
Photo
By Glenn D. Bridges |
Gregg said
Rathie plans to market part of the mill as a warehouse, and rent
office space out of another.
“He also purchased some
undeveloped land around the mill – several hundred acres –
and at some point plans to build a nice residential
community,” Gregg claims.
SJWD Executive Director Mike Caston
had nothing but praise for the entire operation.
“This is the way it ought to be
done – cooperation between different organizations inside and
outside the community,” he lauded. “I wish all of our
projects worked this well. There’s nothing simple about this,
but it’s been a delight.”
Glenn D. Bridges can be reached
at: daddydolphin@charter.net.
|